Originally posted by: Viditor
To be fair, you have to remember that the majority of that delay was a design problem with the first K10s...
Until they had that working just right, they obviously couldn't do a 45nm conversion.
Not trying to be argumentative but IIRC the claim that a 65nm stepping delay inflicted a 45nm process technology delay is one that has only existed in the speculative circles of forums such as this.
Has AMD ever mentioned 65nm Barelona B3 stepping as the root-cause for 45nm timeline being ~12 months lagging Intels? If it has then it slipped my attention.
Not saying it doesn't stand to reason that the Barcelona fixes in B3 stepping had to be accommodated in Shanghai and that no doubt took time as well, but it wasn't a "re-invent the TLB bug solution wheel" for shanghai either as the bulk of the work was done for the initial fix in K10 (presumably).
However we should be clearer in our use of the terms "45nm conversion". I am speaking to the process technology conversion that happens inside the fab, you appear to be referring to the design/layout/tapeout/validation of a 45nm IC which does not occur inside the fab and usually runs parallel to and independent of the 45nm process technology development cycle (up to the point of validation obviously as then you need physical samples from said process technology to move to next cycle...these are what generally get called qual runs)
A delay in 45nm design of Shanghai (induced by incorporating lessons learned from Barcelona in crisis mode fashion) does not require or necessitate a delay in 45nm process technology development and validation...but a dire shortage of cash and resources most certainly would
😉 (and a shanghai delay from barcelona would most certainly stretch the dollars even thinner and thus delay process technology from that threat vector)
Originally posted by: Viditor
That said, I see no reason why they would delay their 32nm chips. You don't need to finish one node to start another...the only downside is that they will lose 9 months of 45nm production, but they can probably hide that in the FabCo changeover anyway.
In fact no one does, that's simply how the entire industry operates. Its the same with fab conversions and product mixes within the same fab. It is kind of a working myth that fabs "convert" from one process technology to another.
Truth is they slowly transition as they bring in the necessary equipment (usually <10% new equipment is needed for a new node versus the existing one) and release it to production. A node transition inside an existing and operating fab can take a fully year to really reach the 50/50 mix cross-over point.
It is also common for the same fab to manufacture 3 or 4 nodes at the same time. So long as all the equipment can be shared and the product in question has a cost structure that precludes it from taking advantage of a shrink owing to the layout, mask set, and validation costs then these things have a way of living for nearly a decade.
At TI we were doing 32nm development in a fab that also housed 45nm development, 65nm production, 90nm production, and a handful of lingering low-volume wafer starts of 130nm production...all in the same 300mm fab. It's not just possible, but unless you've got Intel size resources its pretty much impossible to funtionally operate in any other manner.
That said, the reason 32nm would be delayed because of a 45nm delay (and I say this happen at TI with 130nm -> 90nm) is because the 45nm delay can steal resources from the 32nm parallel development efforts as management attempts to deal with cash flow issues in crisis management mode fashion. Same way a Barcelona issue managed to delay Shanghai if our discussion above is to be considered plausible.