I'm a senior level app administrator. Over the years, our software development crew has written an in-house app that connects to one of my canned apps through the SDK. As a result, before I am allowed to upgrade my app, I have to notify them so they can perform their test plan. I notified them about 7 weeks ago that I had an extremely critical service pack I need to apply, and that they needed to run through their test plan as quickly as possible. My hope was to get the patch applied in 1-2 weeks.
The awesome girl who previously performed the test plan has gone on to bigger responsibilities. It typically took her 1 full business day to perform the plan.
The newish guy was told that this test plan was his primary responsibility. He's had it for 6.5 weeks and still just finished QA testing last week, which means he's just over halfway done. He's the social butterfly type - he barely warms his chair on any given day. He comes in late & leaves early. His boss had "The Talk" with him last week, but I'm not sure it penetrated his skull.
I found out about a week ago that the VP over IT has given my service pack project a high priority with a completion date of no later than the end of July. I've jumped through the hoops with all the stakeholders to get my upgrade scheduled for this Wednesday... I got an email from the idiot that he *promises* the test plan will be complete by COB Thursday.
Not sure what I'm going to do, but once the poopy hits the fan, every person from me up to the VP over IT is going to know the idiot's name.
Thanks for listening.
Love,
NuclearNed
The awesome girl who previously performed the test plan has gone on to bigger responsibilities. It typically took her 1 full business day to perform the plan.
The newish guy was told that this test plan was his primary responsibility. He's had it for 6.5 weeks and still just finished QA testing last week, which means he's just over halfway done. He's the social butterfly type - he barely warms his chair on any given day. He comes in late & leaves early. His boss had "The Talk" with him last week, but I'm not sure it penetrated his skull.
I found out about a week ago that the VP over IT has given my service pack project a high priority with a completion date of no later than the end of July. I've jumped through the hoops with all the stakeholders to get my upgrade scheduled for this Wednesday... I got an email from the idiot that he *promises* the test plan will be complete by COB Thursday.
Not sure what I'm going to do, but once the poopy hits the fan, every person from me up to the VP over IT is going to know the idiot's name.
Thanks for listening.
Love,
NuclearNed