Rant - Remodeling my bathroom - Update - tile setter has been fired

Sho'Nuff

Diamond Member
Jul 12, 2007
6,211
121
106
As some of you know my wife and I are in the process of remodeling our house. We started with our basement last year, and now we have moved on to the bathrooms, garage, and laundry room.

Right now our contractor is in the process of gut remodeling our master bathroom. That bathroom is basically a "P" shape, with the long side of the P being about 7 feet wide and extending from a door to our bedroom about 20 feet to the outer wall of our house. The short side of the P is about 12 feet wide and begins about 10 feet from the door to our bedroom. Because the room is so big, we are planning to relocate our downstairs laundry to a laundry closet in the remodeled space, and to turn the existing laundry room into a nice mudroom entryway from our garage. The toilet is being relocated to a dedicated "toilet room" in in the renovated space, and the existing (small) shower and (huge) jacuzzi tub will be removed and replaced by a huge walk in shower.

The project began about 5 weeks ago. For the first couple weeks the project went very smoothly. Demo, framing, etc. all went off without a hitch and was completed about 3 weeks ago. Then the tile guy arrived and began to "work." I put "work" in quotes because apparently the tile guy believes that "work" means standing around for hours on end talking to his apprentice (his son), making incessant trips to home depot, and punctuating the day without about 50 smoke breaks rather than actually doing anything to lay tile. It took him the better part of a week to cut and install roughly 15 sheets of concrete backerboard. He then started to lay the floor of the bathroom, which is in rectangular 1 foot by 2 foot tiles. After he laid about 10 tiles I could already see that the tiles were out of level and out of alignment, which is no surprise because the nimrod wasn't using a level or spacers! He was trying to eyeball everything!

I complained to our GC, who said he would work everything out. Over the ensuing 5 days, the tile guy appeared to be doing nothing again except muttering to himself and talking with his apprentice. Finally over the past weekend he did some work . . . which basically involved popping all of the tiles he already laid and relaying them "properly."

This week it seems that the tile guy got a burr up his butt, and he actually started making real progress on the floor. He laid all the floor tile two days ago and cordoned off the room, which prevented my wife and I from taking a close look at the laid tiles. Yesterday while we were at work he grouted the entire floor.

Well, you can guess what happened. About 50-60% of the newly laid tiles are out of level! I'll post pics when I get home, but you can clearly see that the tiles are off when you look at them. The short edges of about 50% of the tiles are not level from edge to edge with the short edge of an abutting tile. He also apparently mixed the grout color incorrectly, because instead of the nice warm "tan" grout we wanted and picked out, the grout he installed is nearly white! After seeing the grout I looked at the materials in our garage, and it appears that he did not use one of the color "packets" that came with the grout we selected.

So now I am faced with a lovely situation. I have a "complete" bathroom floor that looks like sh!t and has the wrong grout colors. The schedule for the remodel is already 2 weeks behind because of the tile guy, and I have no confidence that he can correct the issues and actually install the tile properly. In all likelihood the tile will have to be ripped up (hopefully without damaging the radiant heat mats under the floor) and completely redone. Moreover I am sure that the tile guy will argue that the floor is "done" and will want to be paid for it before doing further work. ARGH!!!!!

FWIW, our general contractor has been very good thus far and I am confident that he will work with us to make sure that the install is to our satisfaction. But it is incredibly irritating knowing that I have the least amount of confidence in the skills of the guy who will have the biggest impact on the overall look of the bathroom.

update

So my wife met with our GC this morning re: the tile. To my GC's credit, he took one look at the tile floor and said that it looked like shit without my wife having to say anything. He also said that he bore responsibility as the GC, and that he would do whatever it takes to make the floor right, even if that meant ripping out all of the tile, radiant mats, and subfloor, and reinstalling the whole thing. That said, he is going to move forward with all of the other parts of the job so that the remainder of the schedule is not screwed up. And once everything else is done they will come back and fix the floor.

Cliffs:
-OP hired general contractor to gut remodel master bath.
-GC hired tile guy
-Tile guy is an idiot who is both slow and does not know what he is doing
-Tile guy laid ~10 floor tiles, most of which were out of level.
-OP complained and tile guy reinstalled all of the out of level tiles.
- Subsequently the tile guy laid all of the remainder of the floor in one day and blocked off the room, preventing inspection of the laid tiles.
-The next day tile guy grouted the tiles while OP and wife were at work
- ~50-60% of all of the floor tiles are not level edge to edge, and the grout is the wrong color.
-Project is now weeks behind and OP has no confidence that the tile guy can do the job correctly.
-update GC confirmed that the floor looks like shit and that he will do whatever it takes to fix it. :thumbsup:

update 2 Promised Pic with circles to show high (black) and low (red) spots:

2c52e122-f594-4489-a847-97c91dda25fe.jpg


update 2
Ok so the situation has gotten worse. I mentioned that the tile installer was proceeding with the shower. I went on travel for work on Friday and came back on Sunday to a shower that is an absolute mess. Will post pics of the issues later. I have grout lines that are not lined up, major "lippage," a shower nook that is going to be 2 inches smaller on a side than we discussed, etc. The issues go on and on.

After seeing the state of the shower on Sunday I called the GC and told him that under no circumstances was the current tile setter to continue working on the job, and that we have to have someone else come in. To his credit, the GC agreed on all of the issues I saw and also agreed (without complaint) that a new tile setter was needed. He also said that he was "embarrassed" and at a "boiling point" with the current tile setter. In sum the GC is being a stand up guy, which is great because our experience with him has been nothing short of fantastic thus far (tile excepted).
 
Last edited:

Puppies04

Diamond Member
Apr 25, 2011
5,909
17
76
I would have lost it by now. Speak to the GC tell him you don't like the guys work ethic or quality of work. Explain that you won't be paying for the tiling until it is correctly installed and that you want another contractor bought in.

Think of it this way, if you back down to this BS you are forcing this misery on the next guy who employs him. At least this way the GC might stop using the moran.
 

Jimzz

Diamond Member
Oct 23, 2012
4,399
190
106
Tile work seems to be a skill many "in the field" do not have. My wife and I did most of the tile work for our house and not perfect but good. Well 1 bathroom she let the person gutting it do the work and they, "professionals", did worse work than us.

Its was natural tile so I think they were use to man made with groves/cuts on the bottom not flat stone.
 

Vapid Cabal

Member
Dec 2, 2013
170
10
81
Wow, what a jerk. Most folks who do tile tend to do it correctly the first time, cause it is a bitch to do properly ( and why would you want to do it 2x if you didn't have to).

That tile guy seems like he just doesn't give a rats ass.
 
Last edited:

nickbits

Diamond Member
Mar 10, 2008
4,122
1
81
When m parents were building their house some years ago, my dad had them rip everything out and redo it. That was a lot of wasted material but they had no choice but to eat it.
I tiled my own kitchen and about 10% of the tiles are off level and it bugs me everytime I see them but oh well...
Don't pay until you're happy.
 

vi edit

Elite Member
Super Moderator
Oct 28, 1999
62,484
8,344
126
It's on the GC to make that right. He should have fired the sub after the first couple days of twiddling and shitty work. I don't know what to say about the radiant grid. Is that basically stuck to the concrete board and then they applied the thinset right over it and the tile is set? If so...that's going to suck to to get out. You won't be able to use a spud to scrape up thinset and get a level surface without damaging that grid.

My guess is they'd have to rip everything out.

Got pics of just how crappy of a job they did?
 

Genx87

Lifer
Apr 8, 2002
41,091
513
126
Hilarious. I retiled our bathroom in 3 days. Spent half the day ripping up the old flooring. Then the other half cutting the concrete board and securing to the floor and placing the tiles. The next day was spent actually installing the tiles and grouting. 3rd day some clean up.
 

Greenman

Lifer
Oct 15, 1999
21,751
6,176
136
Tell the GC the work is unacceptable, he'll deal with it.

Did the tile guy start with the floor?
 

Puppies04

Diamond Member
Apr 25, 2011
5,909
17
76
I tiled my own kitchen and about 10% of the tiles are off level and it bugs me everytime I see them but oh well...

I'm trying to work out how this happens?

"Heh honey, that tile isn't level"

"Don't worry the tile adhesive is wet, once it dries and the tile can no longer be removed without a whole crap load of disruption and dust it might magically be level"
 

purbeast0

No Lifer
Sep 13, 2001
53,486
6,325
126
that sucks OP, but it sounds like your GC is a shitty one. we're doing a pretty big backyard renovation right now and while it looks like a warzone back there now, it's slowly starting to come together and i'm confident at the end it will look amazing. hope you get it all worked out.

whatever you do, don't pay the remaining balance to your GC until everything is 100% to satisfaction.
 
Last edited:

vi edit

Elite Member
Super Moderator
Oct 28, 1999
62,484
8,344
126
I tried drawing out the floorplan but failing to put it together. What is real square footage of the area?
 

Insomniator

Diamond Member
Oct 23, 2002
6,294
171
106
How long does it take to rip a finished tile floor back up? A whole day? + the week it took him to put it down? Is this like a $2000 mistake?
 

ajskydiver

Golden Member
Jan 7, 2000
1,147
1
86
Hindsight being 20/20, you should've stopped him the moment you saw him eyeballing and laying tile so poorly.

I'm a DIY guy and have a 6' level, tile spacers, tile levelers, laser level, etc. Ridiculous that a pro doesn't have or use them.

You're going to have to rip it all up and start everything over from scratch. Your heating mats are not going to be saved either.
 

Sho'Nuff

Diamond Member
Jul 12, 2007
6,211
121
106
It's on the GC to make that right. He should have fired the sub after the first couple days of twiddling and shitty work. I don't know what to say about the radiant grid. Is that basically stuck to the concrete board and then they applied the thinset right over it and the tile is set? If so...that's going to suck to to get out. You won't be able to use a spud to scrape up thinset and get a level surface without damaging that grid.

My guess is they'd have to rip everything out.

Got pics of just how crappy of a job they did?

The radiant grid is basically resistive heating wires embedded in a thin fabric mesh. The fabric is laid on the subfloor and adhered with thinset. Then the tile is laid over it.

I have no idea how they are going to get the tiles level at this point without ripping everything out and replacing the subfloor and radiant. The radiant mats are expensive as shit too, as was the tile. Floor tile was $8/square and the radiant mats were ~$1400 bucks (not including install).

I do have pics but will have to post them when i get home.
 

Sho'Nuff

Diamond Member
Jul 12, 2007
6,211
121
106
Hindsight being 20/20, you should've stopped him the moment you saw him eyeballing and laying tile so poorly.

I'm a DIY guy and have a 6' level, tile spacers, tile levelers, laser level, etc. Ridiculous that a pro doesn't have or use them.

You're going to have to rip it all up and start everything over from scratch. Your heating mats are not going to be saved either.

That is what I fear too. FWIW the GC ripped the tile guy a new one after the initial crap install, so I have confidence that the GC will make things right. Which at this point I think will probably involve either firing the tile guy or holding hot coals to his toes.

I knew something was wrong when I saw that the tile guy was using the same $180 rigid tile saw that I bought when I did the tile floor in my kids bath. Shouldn't a professional tile installer have a nice tile saw?
 

Squeetard

Senior member
Nov 13, 2004
815
7
76
Should have got rid of him after those first 10 tiles. Bring your GC in and show him. Tell him to get someone else and redo it. This is a big piss off but you let it go too far OP.

Edit: Also, WTF? I tiled my 2 upstairs bathrooms and a 10x15 foyer in the basement myself, never having done it before. They came out perfect. I don't understand how you could even not get them level? Used the rubber spacers too, way easier than eyeballing.
 
Last edited:

Sho'Nuff

Diamond Member
Jul 12, 2007
6,211
121
106
How long does it take to rip a finished tile floor back up? A whole day? + the week it took him to put it down? Is this like a $2000 mistake?

Potentially more than $2000. Depends on how much of the tile he can salvage and whether radiant and subfloor can continue to be used.

Tile was $8/square * 250 square feet = $2000 not including installation materials.
Radiant mats were $1400 not including install
Existing subfloor was used. No idea how much it would cost to redo.
 

Blackjack200

Lifer
May 28, 2007
15,995
1,688
126
Sounds like the GC needs to sue the tile guy and hire a new one. I worked a couple of years for my father who is a GC, and the mason he used for tile jobs and concrete was a shithead who was unresponsive, slow, expensive, and obnoxious. But my dad still used him because at the end of the day (or week, or month) he did the job right, and it's just that hard to find good subs.
 

Sho'Nuff

Diamond Member
Jul 12, 2007
6,211
121
106
Should have got rid of him after those first 10 tiles. Bring your GC in and show him. Tell him to get someone else and redo it. This is a big piss off but you let it go too far OP.

Edit: Also, WTF? I tiled my 2 upstairs bathrooms and a 10x15 foyer in the basement myself, never having done it before. They came out perfect. I don't understand how you could even not get them level? Used the rubber spacers too, way easier than eyeballing.

How did I let it go too far? I complained after 10 tiles, which were then redone. Subsequently the tile guy tiled the whole floor in one day while I was away, blocked the room off so we could not inspect, and grouted it the next day before we could inspect.

The fact that he sat around for so long was concerning, but it did not lead me to believe that he was incompetent. Just that he did not mind not making much money on a fixed fee job.

I too am amazed that the tiles are so out of level. I tiled my kids bathroom earlier this year. While it did not come out perfect, the tile I installed is level and generally looks great considering it was my first tile job.
 
Last edited:

sswingle

Diamond Member
Mar 2, 2000
7,183
45
91
How does a tile guy block a room off in such a way that the owner of the house is unable to go in and take a look?