Originally posted by: MikeyIs4Dcats
Originally posted by: DaTT
To hang the 4 sheets of board will take maybe 20-30 minutes. Taping will be done in maybe 15 minutes (include mixing the compund add another 10...to be generous). First coat should also be like 20 minutes, second coat 20 minutes, final sanding will also be like 20 minutes.
I do this for a living BTW.
now you've lied to him. There is NO WAY anyone will charge him for only 2 HOURS to do that job. Get real. This is not production work like rocking an entire house, it's a small inefficient project.
A more realistic estimate would be 1MH to rock it, 1MH to apply first coat and clean up, and 1MH for 2nd coat and clean up, 1 MH for 3rd coat and clean up. Allow 2 MH for sanding and final cleanup. But you need to find out how he is charging you....is he charging you travel time for the repeat trips? Are you providing all materials at the location, or does he have to pick them up? If he has to go buy the stuff or move it from your garage to the room being worked on, he will charge you for that time.