- Nov 2, 1999
- 4,821
- 0
- 0
We're getting our electrical panel upgraded from fuses to breakers and wanted to get permit for the work to make sure the job was done correctly. But the contractor said that he'll have to charge $80/hr, min. of 4hrs. to sit and wait for the inspectors to come.
I know I can get the permit myself, but I was wondering if the contractor has to be there as well.
I know I can get the permit myself, but I was wondering if the contractor has to be there as well.