Making a spreadsheet to track some project progress.
The project consists of installing 600 computers. Each computer will get its own line.
I have 4 columns that I want to put check boxes in. Each column will represent part of the job complete, such as computer in place, power in place, network in place etc.
The 4 columns are G, H, I & J. The percentage complete of the tasks in that order are 15%, 15%, 35%, 35%.
The forumula should sum all of the check boxes that are clicked. So if just H is checked, then I get a total of 15%. If H and J are both checked then I should get a total of 50%.
Anyone know how to do this at all? Also looking for a way to add check boxes to each of the excel cells in those 4 columns.
Thanks! 🙂
The project consists of installing 600 computers. Each computer will get its own line.
I have 4 columns that I want to put check boxes in. Each column will represent part of the job complete, such as computer in place, power in place, network in place etc.
The 4 columns are G, H, I & J. The percentage complete of the tasks in that order are 15%, 15%, 35%, 35%.
The forumula should sum all of the check boxes that are clicked. So if just H is checked, then I get a total of 15%. If H and J are both checked then I should get a total of 50%.
Anyone know how to do this at all? Also looking for a way to add check boxes to each of the excel cells in those 4 columns.
Thanks! 🙂