I've mentioned a few times in the past that I'm building a large addition onto our home. About 1400 ft^2!
I'm finally ready to call for the electrical rough-in inspection tomorrow. I'm gonna take the afternoon off to finish up some small nits, and disconnect one circuit that I was already using out of convinence. So far I'm 5/5 passing inspections on the first try (leech-field, foundation, frost-wall, plumbing-base, plumbing rough-in), but I expect this one to be tougher. Wish me luck!
For context ... for a residential electrical rough-in you have to have all your boxes in place, wires pulled & stripped, splices & ground made up, but no fixtures in place.
I'm finally ready to call for the electrical rough-in inspection tomorrow. I'm gonna take the afternoon off to finish up some small nits, and disconnect one circuit that I was already using out of convinence. So far I'm 5/5 passing inspections on the first try (leech-field, foundation, frost-wall, plumbing-base, plumbing rough-in), but I expect this one to be tougher. Wish me luck!
For context ... for a residential electrical rough-in you have to have all your boxes in place, wires pulled & stripped, splices & ground made up, but no fixtures in place.