Texashiker
Lifer
- Dec 18, 2010
- 18,811
- 197
- 106
Ever seen a 500-1000 ton crane?
Fina in Groves Texas (now called Total) had one when they were setting the new towers.
Just getting the crane in place took a couple of weeks, maybe even a month? If I remember right, the refinery had to pour a special reinforced concert slab "just" for the outriggers of the crane. Then the slab had to cure for a couple of weeks, then the crane was moved into place.
Then there are the cranes that help build the offshore drilling rigs, talk about massive.
I would imagine for a refinery of that size to be built inland they would have to actually fabricate those absurdly large sections on or very close to the site which would increase the cost so much that it just isn't feasible.
One of the shops I worked at had a 500 ton lifting capacity (2 - 250 ton overhead cranes), and the shop was right at 1/4 mile long. Part of the shop went over the ship channel. When we shipped really heavy parts out, a barge was brought in, parked under the shop in the water, then the overhead cranes would set the tower in the barge.
Anything up to 50 tons should be fine to transport over the road, but 50 tons is not "that" big of a part.
One heat exchanger shop I worked at, we built a hydrogen service shell and tube heat exchanger for Exxon. The shell was 3 1/2 inches thick, was only about 3 feet in diameter, the exchanger was about 30 feet long, and weighed right at 30 tons. The flanges were something like 18 inches thick.
Last edited: