MS Project Experts - Predecessor "Or" Gates?

Dec 21, 2007
34
0
0
Hi all,

I have a task in an MS Project file that depends on completion of either of two other tasks, i.e. whichever completes first ("or" not "and"). Is there a way to set this up with predecessors, or other technique, without "hardcoding" the one that completes first? I would like to be able to play around with sequence.

Thanks
 

PCDumbass

Senior member
Aug 26, 2002
462
0
71
Hi all,

I have a task in an MS Project file that depends on completion of either of two other tasks, i.e. whichever completes first ("or" not "and"). Is there a way to set this up with predecessors, or other technique, without "hardcoding" the one that completes first? I would like to be able to play around with sequence.

Thanks

You can't get this to work with the simple drag/drop link creation between Gantt Chart bars?