Ok the foundation has been done, poured in 3 separate pieces. The old foundation was a mess. Whoever poured the foundation before did not use any rebar. The soil around the garage is sloped so the left side of the top of the old foundation and the wood framing was 3 inches below the soil and the wood framing was rotted away. The new concrete foundation is 6 inches above the soil and 18 inches below the soil.
But I have a few concerns but the contractor assured me these things will not be an issue.
1) Instead of using ready-mix concrete, they used Quikrete #1101 high strength 80lb bags and mixed themselves using a portable mixer. Would it have been better to use ready-mix from a concrete truck? The contractor said he can't ask the concrete truck to come 3 times because there is a minimum load.
2) The foundation and footers were poured as one single piece. Any concerns here?
3) No vapor barrier was used. I found out today researching online there should be a vapor barrier between the soil and foundation. Should I be concerned here?
4) They stripped the forms and did framing the next day after the concrete was poured. The sill plates were tightened down to the foundation tie downs also. Isn't this too early?
It seems like they are rushing to finish the job quickly. They used a lot of tie downs (1/2" diameter tie downs every 24" apart) and Simpson HDU5 holdowns at each corner. I hope this enough to keep it all together.
1. In general there is no difference between bagged concrete and concrete delivered by truck. Both have to be mixed with the correct amount of water to reach full strength, etc.
2. No concerns here as long as there form work, rebar, and placement of concrete was done competently.
3. In general this is not an issue. Concrete itself does not have to be protected from water vapor. Was a slab poured at the same time? Plastic under the slab is useful for a variety of reasons. Mainly because it helps the concrete cure. It also can help prevent ground water entering the building but that is much more important for a finished space.
4. These small jobs have to be done quickly and efficiently or the contractor does not make a living. There are dangers with working over uncured concrete but they aren't insurmountable. For example, they shouldn't have torqued down the anchor bolts more than finger tight plus a quarter turn or so. You check them at the end of the job.
Nothing here raises any red flags for me.